Case Interview Example – Estimation Question and Answer
I was asked the following management consulting estimation question by a McKinsey interviewer many years ago:
“Estimate how long it would take to move or relocate an average size mountain 10 miles using an average size truck”
Below you will see my answer to this estimation question and the process and rational I use to answer this specific question can be used as a template to practice answering other estimation questions as you prepare for case interviews.
The first thing to realize in an estimation question is that an acceptable answer MUST mention a specific number.
This question was how much time it takes to move an average mountain 1 mile (or something along those lines).
If the answer does not include a specific unit of time like X hours, Y days, Z years, then the answer is not acceptable.
By the way, I use the word “acceptable answer” instead of “correct answer” very deliberately. The interviewer’s evaluation in this type of question is in assessing the approach you took, not necessarily the specific answer you gave.
The next thing to the answer must include is that explicit assumptions must be made.
It is not possible to answer this question without making some assumptions. They key is to EXPLAIN to the interview that you are going to make some assumptions. Once you do and once you make a specific assumption, explain your rationale behind that assumption.
For example, when I was given this question. I knew that I needed to estimate the cubic volume of the mountain. And since the mountain loosely resembles a cone, I knew there was a geometric formula to calculate the volume of a cone–except I did not recall the specific formula off the top off my head.
So my interviewer suggested that I estimate the formula of a cone, which in turn I would use to estimate the volume of an average size mountain, which would then be part of a calculation to estimate the average time it would take to re-locate it.
Notice the estimate that is nested within the estimate here. This is very common. Most important thing is to not get mixed up and confused by your own work.
I find it is useful to just write out the formula that will produce the estimate FIRST, THEN go about making reasonable assumptions.
For the move the mountain case, the formula I wrote up on the white board during my interview was:
volume of mountain / volume of a truck * time per truck trip = total time to move a mountain
I would literally write that on the board. That is the amount of time it would take 1 truck to move an average size mountain 10 miles (the 1 truck is an assumption as well)
Then I went about estimating each of those 3 factors.
Assume the average size mountain is 1 mile tall, 1 mile wide, and the shape of a cone. That’s approximately 5,000 ft in height and base.
I forge the formula to calculate the volume of a cone, but if I eye ball it, it is probably a little more volume than half of a cube of similar size height and base.
The volume of a cube that’s 5,000 ft tall, 5,000 ft wide, and 5,000 ft deep is 125,000,000,000 cubic ft.
Since I’m trying to estimate a CONE, and not a CUBE, I’d then take 125,000,000,000 x 50% (my approximate guess as to how much smaller a cone is vs a cube of approximately the same height, and width and length at the base.
With some slight rounding, that gets us 60,000,000,000.
Then underneath my original formula, I would write the following:
60,000,000,000 cubic ft / volume of a truck * time per truck trip = total time to move mountain
Next, I would move on to estimate the volume of a truck.
The carrying capacity of a cargo truck is the width x length x heightof the cargo container.
I said, well I know those big trucks are a little wider than my car, but not by much since they still must be able to fit into a lane on the freeway. My car sits 3 people across, assuming 2 ft in shoulder width per person, that’s 6 ft of interior space. Let’s add on a little more and assume those big trucks are around 8 ft in width.
I know they are about double the length of most passenger sedans. And lets see if I were to lie down in the driver’s seat to take a nap, I cover most of the interior cabin space. And the hood and trunk of the car combined are about the same length as the interior cabin. I’m a little under 6ft tall, so that makes my car around 12 ft long. If I double that, I get the length of one of those trucks to be 24 ft long. I subtract out say 4 ft for the driver compartment, and that leaves me about 20 ft in length for the cargo area.
Last time I looked, I saw a worker standing in the back of one of the cargo areas, and the cargo area was taller than the person. I figure the cargo container is about 8 ft tall. And since most freeway bridges have signs that say “height 13 ft” and I know those trucks can go under those bridges, assuming an 8ft cargo section and a 4ft for the tires and chassis under the cargo area, that gives me 12 ft…which does seem to triangulate with the height of those underpasses. So I’ll say the cargo section is approximately 8 ft tall.
The volume of the cargo area of an earth moving truck is:
8 ft wide x 20 ft long x 8 ft tall = 1,280 cubic feet
For sake of simplicity, I’m going to round that down to 1,250 cubic feet and plug this number back into my original formula which now reads as follows:
60,000,000,000 cubic foot mountain / 1,250 cubic foot truck capacity * time for truck trip = total time to move a mountain
The only factor missing in our estimate is figuring out the round-trip time for a trip to move 10 miles, drop its load, and return the 10 miles. Let’s figure out the travel time first. Assume the truck travels on the freeway at 60 miles per hour.
For it to travel 10 miles, it does so in 1/6 and hour or 10 minutes. The drive time is 10 minutes to the new location, and 10 minutes returning to the old mountain for a total of 20 minutes. Assume that the off-loading process has been designed to be pretty quick. The load is just “dropped” and then repositioned while the truck is on its return trip (as opposed to being scooped out of the truck, one scoop at time which seems more time consuming).
That means each round trip takes 30 minutes or 0.5 hours.
Let’s go back to our formula again and update it.
60,000,000,000 cubic ft mountain / 1,250 cubic foot track capacity * 0.5 hours per truck trip = total time to move a mountain
Let me do the math now. For the first 2 components of the formula, that works out to about 50,000,000 (50 million truck loads).
50 million truck loads x 0.5 hours, thats 25 million hours to move a mountain.
If we assume a typical day has 25 hours (to make our math a little simpler), that’s 1 million days to move the mountain using only 1 truck. That works out to a bit under 3,000 years
That is the logic I just presented is a pretty good one that would most likely pass most estimation question interviews.
You will notice that for every little component I explain WHY I felt that was a reasonable assumption.
There is a big difference between making a wild assumption vs. a reasonable one. Your goal is to make as reasonable assumption as you can come up with. When you make such an assumption, it is very important you explain WHY you made the assumption you did.
The math is not that complicated (it’s math we all learned before high school) BUT communicating what you are doing is just as important.
It is also important that you do not make a math mistake. I wrote out this example quickly and hopefully I did not make a math mistake.
If I did make a math mistake, I would full expect to get rejected even if I got the logic and assumptions largely right.
That’s just the way it works. Practice your mental math. You DO use it a lot not just in interviews but with clients as well.
504 thoughts on “Estimation Question”
Edit to previous comment: I didn’t answer the question with a time frame before.
Assume that the truck is traveling at 30mph because there is a heavy load and it’s dangerous to drive on normal roads any faster with this load in an average truck. This would take 40 minutes round trip in traveling alone. Also assume that loading the truck (with a machine) would take 10 minutes and unloading the truck (dumping it or using a machine to pull the load off) would take ten minutes, this would be approximately one hour for one full trip. In my previous answer I calculated that there would be 3,125 trips which would mean that the transportation process would take approximately 3,125 hours or just a little over 130 days. This is assuming that the truck consistently makes trips throughout the time frame and is not including stops for gas.
The first step is to determine the area of an “average” size truck bed. I estimate the dimensions of average to be approximately 5ftx6ftx2ft=60ft(square footage). The next step is to determine the area of an average sized mountain. Using the 1/2(pi)(r^2), I estimated the height of the mountain to be 5,000 feet and the radius to be 5,000 feet as well. The area for half of a circle, or a mountain, would be 187,500ft(square footage). The last step is to divide the area of the mountain by the area of the truck bed. My estimated figures allowed to me to deduce that roughly 3,125 trips were needed to move an “average” sized mountain with an “average” sized truck, assuming that you are only using the truck bed to transport the materials and not the inside of the truck as well.
Suppose that an average truck car can hold 5 cubic meters of soil and the height of the mountain is about 1000 meters. The dimension shall be around 800 million cubic meters. This is equivalent to 160 million times of transportation(800 million/5). The driving rate of a truck car is about 70 km per hour. 10 miles equal to 16 km. It will take the truck about 15 minutes to arrive. 2*15 minutes*160 million=4 800 million minutes=9041 years
I would like to approach this problem via simple maths. i would calculate area of mountain first. lets assume mountain as an equilateral triangle. with the help of formula 1/2 area of base * height we can calculate area to be relocated and now calculate the area of an average truck with the help of l*b*h. now by dividing both terms we”ll get no of turns truck has to make to relocate it. It comes out to be 7892100. Now calculate the toatal time taken. Lets say time taken for each loading to be 30 minutes and to reach the area where it has to relocated is 20 minutes and for unloading is 10 minutes. Total time for each single ferry is 1 hour. TOTAL time will be 7892100* 1 hours.
I estimate, based on an average speed of 50 mph, average truck volume of 10 cubic meters vs. average mountain volume of 1000 cubic meters, that it would require 100 back and forth drives (100 times 20 miles) to relocate the mountain – which would take, assuming no stops, breaks and sleeping time, roughly 40 hr.
The concept equation is
number of hours = number of hours per trip * number of trips
assumptions made
(1) From visual imagination of the mountains I saw before, an average size of mountain is about 1,000 typical trucks. Thus it need a truck to run 1,000 round trips to move a mountain
(2) Assuming a truck’s speed is 40 miles per hour. For a round trip of 20 miles, it will need 0.5 hour on the road.
(3) Assuming it take 1.5 hour to load and dump.
Total number of hours = 1000 * (1.5 0.5) = 2000 hours
4 million days
1 truck :
2m*2m*2m = 8m3
average size moutain, in average : 100m * 100m * 50m = 500.000m3
=> in 62500 times with one truck
for each time : fill the truck, drive 10 miles, but it down, drive back : 1h.
so we need 62500 hours.
60 years
Estimating volume of the average mountain to be a cone of 4km height and 4 km base. V=(1/3)*3.14*64 km3=6*10^10 m3
A typical truck has a rectangular load of dimensions 5*3*2m=30m3
No. of turns required by truck=2*10^9
Time to pick up load at deposit at destination = 10 mins=0.16hours
Time to make two way journey from source to desitination=20miles/(60miles per hour)=0.33 hours
Total time for each turn=0.49=0.5hours.
Assuming a 40 hour working week, in one week the truck would do 40/0.5=80 turns=100turns.
No. of weeks required to do 2*10^9 turns= 2*10^7 weeks
Assuming 1 year has 50 weeks, total years=4^*10^5 years=
400,000 years.